Canada's first commercial small modular reactor project is set to exceed its approved C$7.7 billion budget and will no longer achieve its planned October 2030 start of commercial operation.
The first 300 MW BWRX-300 reactor at the Darlington New Nuclear Project is already under construction beside the existing nuclear generating station on Lake Ontario. However, continuing first-of-a-kind engineering work is affecting construction execution, procurement and supply-chain performance, forcing the project team to reassess both cost and schedule.
No revised completion date or final cost estimate has yet been announced. A detailed review of outstanding engineering, design maturity, procurement assumptions, market conditions and possible schedule-recovery measures is expected to be substantially completed by mid-2027.
The original C$7.7 billion allocation includes approximately C$6.1 billion for the first reactor together with around C$1.6 billion of infrastructure, systems and services that would also support three additional planned units.
Construction has nevertheless reached several major civil engineering milestones. A 2.1-million-pound concrete basemat has been installed beneath the reactor building, representing the first nuclear foundation constructed in Canada in more than three decades. Foundation works have also advanced at the turbine building, while a tunnel boring machine has been assembled for construction of the condenser cooling-water tunnel.
Approximately C$2.86 billion had been spent on the project by the end of September 2026.
The central difficulty is the relationship between first-of-a-kind engineering and construction. Unlike later repeat units, the first reactor must establish the detailed design, interfaces, procurement sequence and construction methodology that subsequent units are expected to reproduce.
If engineering packages continue evolving after physical construction has started, changes can affect procurement, sequencing and work already planned in the field. The resulting delays can propagate through dependent construction activities even when visible progress continues elsewhere on site.
This distinction is particularly important for small modular reactors because much of their proposed economic advantage depends on standardisation and repetition. Later units are expected to benefit from a mature design, established supply chain and lessons learned during construction of the first reactor.
The schedule uncertainty has also reached Ontario's electricity planning. Forecast generation previously expected from the reactor in 2030 and 2031 has been removed from the project's current regulatory application, although this does not establish a new commissioning date.
The wider Darlington programme still envisages four BWRX-300 reactors, potentially providing approximately 1,200 MW of generating capacity if all units proceed.
The first unit therefore remains critical not only as an individual nuclear project but as the reference construction programme for the three proposed repeat reactors. Its revised cost and schedule, together with evidence of design maturity and construction learning, will strongly influence how confidently the later units can be planned.
The next major milestone will be the mid-2027 reassessment, when the extent of the cost increase, revised construction programme and implications for subsequent reactors are expected to become clearer.
Sources: enr.com, cleantechnica.com, power-eng.com
Taiwan was struck on Wednesday, April 3, 2024, by the most powerful earthquake it has experienced i...
Load bearing masonry construction is a building technique in which wall elements are used as the fra...
The sudden collapse of the Carola Bridge in Dresden on September 11, 2024, highlights the critical...
A small Japanese company has developed a special powder that could improve water quality in developi...
At optimal growing conditions, each acre in the greenhouse yields as much lettuce as 10 outdoor acr...
As air travel rebounds and infrastructure demands rise, U.S. airports are undergoing massive transf...
Bridges are critical components of transportation networks, yet their maintenance often relies on r...
Imagine traveling from New York to London in just 54 minutes—a journey that currently takes over se...
Construction of the Torre Rise skyscraper in Monterrey has reached a major milestone, with the stru...